Tap any paragraph to write a margin note. Your notes collect in the Desk below the text and file under cases with @. The side-by-side margin rail opens on a larger screen.

Code · CFR · Title 30 — Mineral Resources · Part 817 · § 817.46

§ 817.46. Hydrologic balance: Siltation structures.

707 words·~3 min read·/us/cfr/t30/s§ 817.46·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)For the purposes of this section only, disturbed areas shall not include those areas---
(1)In which the only surface mining activities include diversion ditches, siltation structures, or roads that are designed, constructed and maintained in accordance with this part; and
(2)For which the upstream area is not otherwise distributed by the operator.
(b)General requirements.
(1)Additional contributions of suspended solids and sediment to streamflow or runoff outside the permit area shall be prevented to the extent possible using the best technology currently available.
(2)Siltation structures for an area shall be constructed before beginning any underground mining activities in that area, and upon construction shall be certified by a qualified registered professional engineer, or, in any State which authorizes land surveyors to prepare and certify plans in accordance with § 784.16(a) of this chapter, a qualified registered professional land surveyor, to be constructed as designed and as approved in the reclamation plan.
(3)Any siltation structure which impounds water shall be designed, constructed and maintained in accordance with § 817.49 of this chapter.
(4)Siltation structures shall be maintained until removal is authorized by the regulatory authority and the disturbed area has been stabilized and revegetated. In no case shall the structure be removed sooner than 2 years after the last augmented seeding.
(5)When the siltation structure is removed, the land on which the siltation structure was located shall be regraded and revegetated in accordance with the reclamation plan and §§ 817.111 through 817.116 of this chapter. Sedimentation ponds approved by the regulatory authority for retention as permanent impoundments may be exempted from this requirement.
(6)Any point-source discharge of water from underground workings to surface waters which does not meet the effluent limitations of § 817.42 shall be passed through a siltation structure before leaving the permit area.
(c)Sedimentation ponds.
(1)Sedimentation ponds, when used, shall---
(i)Be used individually or in series;
(ii)Be located as near as possible to the distrubed area and out of perennial streams unless approved by the regulatory authority; and
(iii)Be designed, constructed, and maintained to---
(A)Provide adequate sediment storage volume;
(B)Provide adequate detention time to allow the effluent from the ponds to meet State and Federal effluent limitations;
(C)Contain or treat the 10-year, 24-hour precipitation event ("design event") unless a lesser design event is approved by the regulatory authority based on terrain, climate, other site-specific conditions and on a demonstration by the operator that the effluent limitations of § 817.42 will be met;
(D)Provide a nonclogging dewatering device adequate to maintain the detention time required under paragraph (c)(1)(iii)(B) of this section;
(E)Minimize, to the extent possible, short circuiting;
(F)Provide periodic sediment removal sufficient to maintain adequate volume for the design event;
(G)Ensure against excessive settlement;
(H)Be free of sod, large roots, frozen soil, and acid- or toxic-forming coal-processing waste; and
(I)Be compacted properly.
(2)Spillways. A sedimentation pond shall include either a combination of principal and emergency spillways or single spillway configured as specified in § 817.49(a)(9).
(d)Other treatment facilities.
(1)Other treatment facilities shall be designed to treat the 10-year, 24-hour precipitation even unless a lesser design event is approved by the regulatory authority based on terrain, climate, other site-specific conditions and a demonstration by the operator that the effluent limitations of § 817.42 will met.
(2)Other treatment facilities shall be designed in accordance with the applicable requirements of paragraph
(c)of this section.
(e)Exemptions. Exemptions to the requirements of this section may be granted if---
(1)The disturbed drainage area within the total disturbed area is small; and
(2)The operator demonstrates that siltation structures and alternate sediment control measures are not necessary for drainage from the disturbed drainage areas to meet the effluent limitations under § 817.42 and the applicable State and Federal water quality standards for the receiving waters. \[48 FR 44051, Sept. 26, 1983, as amended at 53 FR 43607, Oct. 27, 1988; 59 FR 53030, Oct. 20, 1994; 73 FR 75884, Dec. 12, 2008; 75 FR 60275, Sept. 29, 2010; 79 FR 76232, Dec. 22, 2014; 81 FR 93418, Dec. 20, 2016; 82 FR 54999, Nov. 17, 2017; 90 FR 54577, Nov. 28, 2025\]
Connections5 cite this
Citation graph
cites case law
§ 817.46
Hydrologic balance: Siltation structures.
Fed. Reg.×5
Cites 0Cited by 5 across 1 source
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.